The unit 2 of Vietnam Srepok 3 hydropower plant put into 28 days reliability run test

Source: Author: Date:2010-10-09【Font:B M S

Just after successful completion of commissioning test, the unit 2 of Vietnam Srepok 3 hydropower plant was put into 28 days reliability run test on Oct 6th 2010, whose complete equipments and technical service is supplied by CNTIC, preparing for the final acceptance.

On the preparation meeting Oct 5th, customer point out that the installation and commissioning of Unit 2 refresh three records of middle and big range hydropower plant in Vietnam:

1)       The interval time of generating and synchronizing between Unit 1 June 25th 2010 and Unit 2 Sept 24th 2010 makes the shortest duration, which only costs 90 days;

2)       It only spend 35 days from generator rotor lowering into the pit to the final generating and synchronizing , which is the shortest record in Vietnam;

3)       The duration from the unit initial run Sept 19th to the generating and synchronizing Sept 24th creates the fastest record in Viet Nam, which only takes 5 days;

Customer give the highly comment to the performance of CNTIC and express the appreciation of CNTIC’s hardworking and support during the installation and commissioning of Unit 2.

At present, the project is near the end and contract closeout work starts.