CNTIC Signs the Contract for the Energy Efficiency Improvement Project of Bangladesh Germany-loaned 230kV and 132kV Power Grids

Source: Author: Date:2020-06-09【Font:B M S



On June 8, CNTIC and Power Grid Company of Bangladesh (PGCB) signed the EPC contract for the energy efficiency improvement project of Bangladesh Germany-loaned 230kV and 132kV power grids.

The project is the largest one among the series supported by Kreditanstalt für Wiederaufbau (KfW) Bankengruppe, including the construction of four new 230/132 kV GIS substations and the renovation and expansion of four 230/132 kV AIS substations. CNTIC is responsible for the overall design, procurement, construction, commissioning, and trial operation.